Say I set a baseline for my software development project. As people
use the timesheet, I can measure revisions to the ETC when estimated
durations in the baseline fall short of actuals.
How do I recognize when a task finishes early, resulting in a downward
revision to the ETC? Can I mark a task as complete (without altering
the actual work value) and lock down my users from recording time to
the task?