We have 2 enterprise calendars, one for standard working hours and the other
for after hours and weekends. We have project tasks that require
after-hours work. Is there a way to assign resources to a task which
utilizes the after hour calendar, without having to edit the resources
calendar.
For example we have one tasks identified as a weekend activity, assigned the
after-hours calendar to it, without any problem. However, when we assigned
a resource, which used the standard calendar, the date changed to the
following Monday
We need to schedule after-hours work based on task for any given resource.
What's the easiest way to do this?
Thank you in advance,
Andy
for after hours and weekends. We have project tasks that require
after-hours work. Is there a way to assign resources to a task which
utilizes the after hour calendar, without having to edit the resources
calendar.
For example we have one tasks identified as a weekend activity, assigned the
after-hours calendar to it, without any problem. However, when we assigned
a resource, which used the standard calendar, the date changed to the
following Monday
We need to schedule after-hours work based on task for any given resource.
What's the easiest way to do this?
Thank you in advance,
Andy