L
Lbrown11
I am statusing milestones (zero duration) in MS Project 2003 Professional by
entering the Actual Finish date field. When I enter the Actual Finish date,
even if it is the same as the Baseline Finish - Project is changing the
Duration to 1 day, which is then, in turn, causing Actual Work to be
populated with 8 hours. With no resources loaded in those milestones, how is
actual work being automatically populated and how do I stop this? It is
making my Actual Work numbers incorrect in reports.
entering the Actual Finish date field. When I enter the Actual Finish date,
even if it is the same as the Baseline Finish - Project is changing the
Duration to 1 day, which is then, in turn, causing Actual Work to be
populated with 8 hours. With no resources loaded in those milestones, how is
actual work being automatically populated and how do I stop this? It is
making my Actual Work numbers incorrect in reports.