Entering a project task in PWA doesn't account for resource max units allocated for the Project

M

mlv

Hello,
I have a ePM user asking why if he enters a project task in PWA does i
not check the resource max units allocation the same way as when h
enters a task in Project Professional.
For example:
You have a project where resource A is 50% allocated. When you create
task in Project Professional for this resource, the resource allocatio
is set to 50%.
Create a task under the same project in PWA, submit and approve th
task.
Open project professional and view the task information for the tas
entered in PWA, why is the resource allocation set to 100% instead o
50% set for this resource?
Thanks
Molli
 
M

Mike Glen

Hi Mollie,

Try posting on the microsoft.public.project.server newsgroup (forum). Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP



Hello,
I have a ePM user asking why if he enters a project task in PWA does it
not check the resource max units allocation the same way as when he
enters a task in Project Professional.
For example:
You have a project where resource A is 50% allocated. When you create a
task in Project Professional for this resource, the resource allocation
is set to 50%.
Create a task under the same project in PWA, submit and approve the
task.
Open project professional and view the task information for the task
entered in PWA, why is the resource allocation set to 100% instead of
50% set for this resource?
Thanks
Mollie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top