BlaiseR
I have Fixed Units tasks (not Effort Driven) and the Options "Move end of
completed parts after status date back to status date" and "Move start of
remaining parts before status date forward to status date" and "Split
in-progress tasks" set. When I update a task status by increasing the "%
Complete" manually, tasks split as expected, pushing the remaining work in a
task to start at the Status Date (or Current Date, if Status Date is not
set). However, if I go into the Task Usage view and enter Actual Hours for
that same task, the "% Complete" updates, but the task DOES NOT split, and
leave remaining work in the past, before the status date. This does not seem
right. Am I missing a setting somewhere?
completed parts after status date back to status date" and "Move start of
remaining parts before status date forward to status date" and "Split
in-progress tasks" set. When I update a task status by increasing the "%
Complete" manually, tasks split as expected, pushing the remaining work in a
task to start at the Status Date (or Current Date, if Status Date is not
set). However, if I go into the Task Usage view and enter Actual Hours for
that same task, the "% Complete" updates, but the task DOES NOT split, and
leave remaining work in the past, before the status date. This does not seem
right. Am I missing a setting somewhere?