M
Mike
In Customizing Project Web Access; Under the section Specifying default
method for reporting tasks....when I change the settings from Percent Work
Complete to Hours of work done per hour, per day, per week......I still can
not enter Actual Work on the My Tasks timesheet view of PWA. Do I have to
republish the project plans for the changes to take affect and the Actual
Work field to accept data?
method for reporting tasks....when I change the settings from Percent Work
Complete to Hours of work done per hour, per day, per week......I still can
not enter Actual Work on the My Tasks timesheet view of PWA. Do I have to
republish the project plans for the changes to take affect and the Actual
Work field to accept data?