B
Babar
Hi,
It will be easier to explain the problem that I am facing through an
example:
Lets say I have a task (Install a pull-down screen) which takes 1.5hr
with 1 resource. Suppose I assign 2 resources to it, so it should
finish in 45min with effort-driven turned on. Also, the task has fixed
units = 100units. Also, this task has a predecessor.
Now the resources finished the task in 30min and they enter these
actual numbers. However, when the Project updates the information, it
changes the duration to 0.9hrs (54min). I don't understand why it does
that when it should adjust the duration to 30min.
Does anybody know the reason why Project does that? I would appreciate
your response.
Thank you.
Sincerely,
Babar
It will be easier to explain the problem that I am facing through an
example:
Lets say I have a task (Install a pull-down screen) which takes 1.5hr
with 1 resource. Suppose I assign 2 resources to it, so it should
finish in 45min with effort-driven turned on. Also, the task has fixed
units = 100units. Also, this task has a predecessor.
Now the resources finished the task in 30min and they enter these
actual numbers. However, when the Project updates the information, it
changes the duration to 0.9hrs (54min). I don't understand why it does
that when it should adjust the duration to 30min.
Does anybody know the reason why Project does that? I would appreciate
your response.
Thank you.
Sincerely,
Babar