C
Chris
Hi there
The Organisation where i work uses Timesheets & Managed Periods.
Where a Task in a plan will be done by an external resource i enter the
duration and allocate it to the resource. In these circumstances the
Resource i allocate the task to is set as a Generic Resource.
These Generic Resources will never fill a timesheet in however as the
Project Manager i would like to record when the task started, finished and if
it 100 % complete - therefore providing a simple record. I will never know
what hours on what days were spent on the task so do not want to enter
actuals via the timesheet.
When ever i enter start & end date and % complete i am told that it will be
overwritten when synching with actuals from the tmiesheet!
Can anyone advise how i can achieve this or point out where i am going wrong.
Regards
The Organisation where i work uses Timesheets & Managed Periods.
Where a Task in a plan will be done by an external resource i enter the
duration and allocate it to the resource. In these circumstances the
Resource i allocate the task to is set as a Generic Resource.
These Generic Resources will never fill a timesheet in however as the
Project Manager i would like to record when the task started, finished and if
it 100 % complete - therefore providing a simple record. I will never know
what hours on what days were spent on the task so do not want to enter
actuals via the timesheet.
When ever i enter start & end date and % complete i am told that it will be
overwritten when synching with actuals from the tmiesheet!
Can anyone advise how i can achieve this or point out where i am going wrong.
Regards