C
CK
Hi,
Several of my resources will receive time and half on Saturdays and double
time on Holidays. If a task takes 4 weeks including 4 Saturdays, how do I
enter the time and half for those Saturdays. It doesn't seem that the cost
table would be effective for this process and adding a fixed cost does not
paint the true picture.
Thanks for your help.
Several of my resources will receive time and half on Saturdays and double
time on Holidays. If a task takes 4 weeks including 4 Saturdays, how do I
enter the time and half for those Saturdays. It doesn't seem that the cost
table would be effective for this process and adding a fixed cost does not
paint the true picture.
Thanks for your help.