entering days in timesheet, wrongly translated to hour

K

Kurt Verhaegen

We have resources which have a calendar and working regime of 40 hours/week
and others who have a calendar and working regime of 37hours/week.
If we publish a project, and the users are filling in their timesheet, but
instead of filling in 8h or 7.4h per day, they enter 1d, the system will
translate it to 8h instead of taking the correct resource calendar.
It seems that the system takes the task calendar or project calendar which
is wrong from the standpoint of timesheet and entering your actuals.

Anybody experience on how to get a correct translation of days to hours when
entering actuals in the timesheet?

Tx, Kurt
 
R

Reid McTaggart

The solution is to train users to enter hours, not days, in their timesheets.

Your system has a single definition of the number of work hours in a day,
and in your case, that is 8 hours. so, anyone who enters 1 day of work is
marked down for 8 hours of work.
--
Reid McTaggart
(e-mail address removed)
Alegient, Inc.
Microsoft Certified Partner
Project Server Experts
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top