P
PeterH
When I enter the work for a task (set to Fixed Units), the duration (which is
defaulted to 1 day?) doesn't change. When I select a resource to assign to
the task, the duration still remains the same and the resource units change
(eg. if I enter 4 hours work, the duration remains as '1 day?' but the
resource shows "Resource name[50%]".
If I then re-select the resource for the task, the duration changes to 0.5
days as expected.
Alternatively, if I select the resource first, then enter the work, the
duration changes correctly to 0.5 days and the resource units remain at 100%.
Can anyone explain why this happens? I want to be able to enter the
estimated effort for all the tasks before I assigne resources but I don't
seem to be able to.
Please note that the default task Type for the project is Fixed Units.
defaulted to 1 day?) doesn't change. When I select a resource to assign to
the task, the duration still remains the same and the resource units change
(eg. if I enter 4 hours work, the duration remains as '1 day?' but the
resource shows "Resource name[50%]".
If I then re-select the resource for the task, the duration changes to 0.5
days as expected.
Alternatively, if I select the resource first, then enter the work, the
duration changes correctly to 0.5 days and the resource units remain at 100%.
Can anyone explain why this happens? I want to be able to enter the
estimated effort for all the tasks before I assigne resources but I don't
seem to be able to.
Please note that the default task Type for the project is Fixed Units.