C
Clive
Say I want to put slack into my plan - overall 10%.
And say I want that to be 10% on the duration of each task (I am
assuming that 10% slack per task results in 10% slack / tolerance of
duration overall - that may not be true)
Every task has a target end date. I added, say, 5 days slack to make a
tolerable end date.
Say the expected end date for a task slips 2 days later than the target
end date. What tools are available in MS-Project so that in the plan
the slack gets "consumed" i.e in this situation the task is 2 days late
finishing but we are left with 3 days slack. The "tolerable" end date
does not slip until I have consumed the explicit 5 days slack.
Thanks
Clive
And say I want that to be 10% on the duration of each task (I am
assuming that 10% slack per task results in 10% slack / tolerance of
duration overall - that may not be true)
Every task has a target end date. I added, say, 5 days slack to make a
tolerable end date.
Say the expected end date for a task slips 2 days later than the target
end date. What tools are available in MS-Project so that in the plan
the slack gets "consumed" i.e in this situation the task is 2 days late
finishing but we are left with 3 days slack. The "tolerable" end date
does not slip until I have consumed the explicit 5 days slack.
Thanks
Clive