Entering project expenses

D

dumbo18

Hi,

Is there any way that users who are assigned to some project tasks can
enter task cost (like hotel expenses) through PWA (Project Server
2007)? I have defined cost resource for this task, but I can't find a
way to use it within PWA.

Thanks
 
D

Dale Howard [MVP]

dumbo18 --

No, you need to enter those expenses in the actual Microsoft Project plan.
Sorry.
 