Glenn
I have a task which has no link to any other task.
If I enter a constraint of Finish No Later Than 12/10/04 and list a duration
of 10d under the Advanced tab and then in the General tab I enter a Start
Date of 06/15/04 and a Finish Date of 12/01/04 then obviously the task will
be starting and then stopping but what happens is that Project complains my
task is linked to another task (WHICH IT IS NOT) and it then sets my Finish
Date to 09/11/05 which is beyond my Project End Date of 09/05/05.
Do I have gremlins in my machine or am I missing something?
Thanks for any assistance.
glenn
If I enter a constraint of Finish No Later Than 12/10/04 and list a duration
of 10d under the Advanced tab and then in the General tab I enter a Start
Date of 06/15/04 and a Finish Date of 12/01/04 then obviously the task will
be starting and then stopping but what happens is that Project complains my
task is linked to another task (WHICH IT IS NOT) and it then sets my Finish
Date to 09/11/05 which is beyond my Project End Date of 09/05/05.
Do I have gremlins in my machine or am I missing something?
Thanks for any assistance.
glenn