S
Steve
We have recently enbaled time tracking in PWA:
* Specify the default method for reporting progress on tasks -> Hours of
work done per day or per week
* Lock down defaults -> Allow project managers to change the default method
for reporting progress..
* Time period settings: -> Week starts on: Sunday
* Non Managed Periods - Allow Project and Project Web Access users to
update actuals.
* The default time periods displayed in resources' timesheets. -> Weekly
* Resources should report their hours worked every day
Here's the problem: Existing tasks do not permit entry of time. New task
do. If a resrouce is removed from a task and then added back again, then the
task permits entry of time.
How do we allow tmie entry for existing tasks en masse?
Thanks,
Steve
* Specify the default method for reporting progress on tasks -> Hours of
work done per day or per week
* Lock down defaults -> Allow project managers to change the default method
for reporting progress..
* Time period settings: -> Week starts on: Sunday
* Non Managed Periods - Allow Project and Project Web Access users to
update actuals.
* The default time periods displayed in resources' timesheets. -> Weekly
* Resources should report their hours worked every day
Here's the problem: Existing tasks do not permit entry of time. New task
do. If a resrouce is removed from a task and then added back again, then the
task permits entry of time.
How do we allow tmie entry for existing tasks en masse?
Thanks,
Steve