A
Amy
I cannot figure out why tasks that show flat leveling schedule themselves as
strange variations in the resource usage view. A 5 hour task over 5 days
seems to be scheduled as .78, 2.1, .9 etc. Why would that be? I am changing
them back manually but they often reset themselves. I dont use leveling. Is
it ok to use resource usage view to schedule people? I am using this as a
master plan covering 30+ projects over 18 months. I am trying to allocate
them broadly to different work. But their usages is all over the place based
on these strange allocations of time.
Second issue is that I have been cutting and pasting plans into the master
plan but i just realized now that it is changing dates. I dont know why-
cannot find any predecessors that would cause that. Im perplexed. I guess I
should move to inserting as sub projects but then it doubles my resources. I
have about 10 project managers submitting various plans, we do not have
project server. Is my only option to create a resource pool?
strange variations in the resource usage view. A 5 hour task over 5 days
seems to be scheduled as .78, 2.1, .9 etc. Why would that be? I am changing
them back manually but they often reset themselves. I dont use leveling. Is
it ok to use resource usage view to schedule people? I am using this as a
master plan covering 30+ projects over 18 months. I am trying to allocate
them broadly to different work. But their usages is all over the place based
on these strange allocations of time.
Second issue is that I have been cutting and pasting plans into the master
plan but i just realized now that it is changing dates. I dont know why-
cannot find any predecessors that would cause that. Im perplexed. I guess I
should move to inserting as sub projects but then it doubles my resources. I
have about 10 project managers submitting various plans, we do not have
project server. Is my only option to create a resource pool?