Anthony --
Yours is a good question. Thanks for asking. I am one of those who
recommends entering 0h on an in-progress task when no Actual Work was
performed during a time period. Therefore, consider the following scenario:
I am assigned to work full-time on a 40-hour task beginning on Monday and
ending on Friday. I worked 8 hours on this task on Monday and 8 hours on
Tuesday. On Wednesday and Thursday I was pulled off this project to to
perform work that is not part of any other project. On Friday, I worked 8
hours again on the original project. How should I enter actuals for the
week? There are two choices:
1. I can enter 8 hours on Monday, Tuesday, and Friday only, and the system
will leave blanks in the cells for Wednesday and Thursday. When the PM sees
the update on his/her Updates page in PWA, the timsheet will show actuals on
Monday, Tuesday, and Friday, with blanks on Wednesday and Thursday. When
the PM updates the task update into the Microsoft Project plan, the system
will enter 8 hours on Monday, 8 hours on Tuesday, 0 hours on Wednesday, 0
hours on Thursday, and 8 hours on Friday. The Gantt Chart will show a task
split where no work was performed on Wednesday and Thursday.
2. I can enter 8 hours on Monday, Tuesday, and Friday only, and 0 hours on
Wednesday and Thursday. I can also enter a Note on the task to document the
reason for performing no work on those two days. The PM will be able to see
the hours on each day on the Updates page and will be able to read my task
Note to be able to understand why I performed no work on those two days.
After updating the task update into the Microsoft Project plan, the result
will be identical to the result in option #1.
Of the two, I much prefer option #2 because the reporting is explicit and
nothing is left to doubt. The addition of the task Note is important and
should not be ignored. Obviously, I could have added a task Note in option
#1 above, but if your client thinks it is too much work to put a 0 in a cell
on the timesheet, I presume it would be way too much work to add a Note
also.
Regarding your section question about vacation, the Resource Pool
administrator should enter those 2 weeks of vacation as nonworking time on
the resource's personal calendar in the Enterprise Resource Pool, and add a
Note to document the reason for the nonworking time. The next time a PM
opens any project in which the vacationing resource is assigned to tasks
during the 2 weeks of vacation, the system will automatically reschedule
that person's uncompleted work in the project until after the vacation.
After the PM publishes the latest schedule changes, the system will
reschedule the resource's work on his/her PWA timesheet as well. Hope this
helps.