Entering Zero Hours in PWA

S

Sinister

At my company we're using Project Web Access to enter in our actual hours on
a day to day basis. Now, If I have my work hours looking something like this:

Mon Tue Wed
WORK 8 8 8

and I enter the following in as actual hours in PWA:

Mon Tue Wed
ACTUAL WORK 5 8 8

Then after the schedule owner accepts the updates, Project Pro will look
something like this:

Mon Tue Wed Thr
WORK 5 8 8 3
ACTUAL WORK 5 8 8

Which is what it's supposed to do, but if someone enters in zero hours in
Project Web the work hours don't adjust to compensate for not doing any work
on that day.

Has anyone else encountered this, and what did you do to fix it?
 
S

Sinister

Something I discovered, this only happens if you enter zero hours on the
first day that you are to start work.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top