S
Sara
Hi
I am a new Project administrator and am trying to find the relationship the
enterprise calendars. We use project 2003.
Here's the situation:
1. Resource calendar
We have enterprise resources with different calendar set up like Japan,
India and China, etc. The calendars have been set up in the enterprise
resource pool. EX) Japan calendar: 9am-5pm(1hr break)-7hrs/day; India
calendar: 8am-6pm (1hr break)-9hrs/day
2. Project calendar
We have some project gantts with "Japan" calendar, and others with
"standard" calendar, which I believe is default.
3. Task calendar
Task calendar has not set up so I guess it's "standard" calendar.
*What is the priority of those calendars?
*We have a problem with resources with "India" calendar assigned to the
project gantt with "Japan" calendar.
Any suggestion and advice would be greatly appreciated.
Thank you in advance.
I am a new Project administrator and am trying to find the relationship the
enterprise calendars. We use project 2003.
Here's the situation:
1. Resource calendar
We have enterprise resources with different calendar set up like Japan,
India and China, etc. The calendars have been set up in the enterprise
resource pool. EX) Japan calendar: 9am-5pm(1hr break)-7hrs/day; India
calendar: 8am-6pm (1hr break)-9hrs/day
2. Project calendar
We have some project gantts with "Japan" calendar, and others with
"standard" calendar, which I believe is default.
3. Task calendar
Task calendar has not set up so I guess it's "standard" calendar.
*What is the priority of those calendars?
*We have a problem with resources with "India" calendar assigned to the
project gantt with "Japan" calendar.
Any suggestion and advice would be greatly appreciated.
Thank you in advance.