I am running a demo of Project Server 2007 on Windows Server 2k3 x64. Client
is Vista Business 32 bit SP1, Project Professional 2007 SP2. Project Server
is on SP2 (Build # 12.0.0.6421) on a single server install.
We have created a project using enterprise calendars. We get the calendar
created and setup for 11 hr days (6 AM – 11:30 AM, 12 PM – 5:30 PM). We
apply this calendar to the project as well as the work resources.
The problem we are having is that when we schedule a task to take any more
than 9 hrs the task will take 2 days on the project. We have tried to
verify everywhere that we can think of that the calendar is showing the 11 hr
day and it appears to be correct from everything I have read. If we click on
working time for resources it shows the correct schedule (11 hr day) but for
some reason it doesn’t stick within the project schedule.
As a side note when I was looking into the enterprise calendar that we have
setup for this project I inadvertently setup it up as a 6 1/2 hr work day (6
AM – 11:30 AM, 12 PM – 1 PM) and it did reflect on the project 9 hr tasks
would now take 2 days until I changed it back to the previous 11 hr day
setting.
FWIW it is also only on this project. Any other project that we have
created for testing purposes as after this it appears to work.
Any help would be greatly appreciated
Thanks,
Joe
is Vista Business 32 bit SP1, Project Professional 2007 SP2. Project Server
is on SP2 (Build # 12.0.0.6421) on a single server install.
We have created a project using enterprise calendars. We get the calendar
created and setup for 11 hr days (6 AM – 11:30 AM, 12 PM – 5:30 PM). We
apply this calendar to the project as well as the work resources.
The problem we are having is that when we schedule a task to take any more
than 9 hrs the task will take 2 days on the project. We have tried to
verify everywhere that we can think of that the calendar is showing the 11 hr
day and it appears to be correct from everything I have read. If we click on
working time for resources it shows the correct schedule (11 hr day) but for
some reason it doesn’t stick within the project schedule.
As a side note when I was looking into the enterprise calendar that we have
setup for this project I inadvertently setup it up as a 6 1/2 hr work day (6
AM – 11:30 AM, 12 PM – 1 PM) and it did reflect on the project 9 hr tasks
would now take 2 days until I changed it back to the previous 11 hr day
setting.
FWIW it is also only on this project. Any other project that we have
created for testing purposes as after this it appears to work.
Any help would be greatly appreciated
Thanks,
Joe