R
rayis
SOME BACKGROUN
We are using an Enterprise Calendar with the following Working Hour
Sunday - Wednesday 8:00 AM to 4:00 P
Thursday 8:00 AM to 3:00 P
Fridays & Saturdays are Holiday
The Calendar Tab under Tool | Options menu has the following detial
Week Start on - Sunda
Default Start Time - 8:00 A
Default Finish Time - 4:00 P
Hours Per Day - 8 Hour
Hours Per Week - 39 Hours (because 1 hour short in Thursday
MY PROBLE
IF I assign a task on a thursday
The task start from 8:00 AM Thursday and Finish on 9:00 AM nex
working day (It suppose to finish on the same day
How can I solve this problem
Please help
We are using an Enterprise Calendar with the following Working Hour
Sunday - Wednesday 8:00 AM to 4:00 P
Thursday 8:00 AM to 3:00 P
Fridays & Saturdays are Holiday
The Calendar Tab under Tool | Options menu has the following detial
Week Start on - Sunda
Default Start Time - 8:00 A
Default Finish Time - 4:00 P
Hours Per Day - 8 Hour
Hours Per Week - 39 Hours (because 1 hour short in Thursday
MY PROBLE
IF I assign a task on a thursday
The task start from 8:00 AM Thursday and Finish on 9:00 AM nex
working day (It suppose to finish on the same day
How can I solve this problem
Please help