Enterprise Calendar

P

Priyu Nayak

Is there anyway I can change the working time of all the resources in the
resource pool without changing each individual's working time? What I need to
do is change the work time from 8-5 to 9-6. So, can I create a new calendar
that would apply to the resource pool instead of the default/standard
calendar?
 
D

Dale Howard [MVP]

Priyu --

Yes, you can create a new calendar in the Enterprise Global file to reflect
this schedule. Then you would need to set this new calendar as the Base
Calendar for every resource in the Enterprise Resource Pool. You can speed
up the process by using the fill handle to copy the calendar value from the
first cell into each successive following cell. Hope this helps.
 
P

Priyu Nayak

thanks.

Dale Howard said:
Priyu --

Yes, you can create a new calendar in the Enterprise Global file to reflect
this schedule. Then you would need to set this new calendar as the Base
Calendar for every resource in the Enterprise Resource Pool. You can speed
up the process by using the fill handle to copy the calendar value from the
first cell into each successive following cell. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top