We have Enterprise standard calendar set up to reflect our company working
hours and publich holidays, but whenever I saved a project schedule offline,
the working hours on the calendar are kept the same but it loses all the
public holidays initially marked as non-working times in the enterprise
calendar.
Is there anyway that I could maintain the calendar set up as the enterprise
one when I save the project schedule offline?
Any ideas or suggestions are much appreciated.
Regards,
JB
hours and publich holidays, but whenever I saved a project schedule offline,
the working hours on the calendar are kept the same but it loses all the
public holidays initially marked as non-working times in the enterprise
calendar.
Is there anyway that I could maintain the calendar set up as the enterprise
one when I save the project schedule offline?