Enterprise Calendars in Project Server 2007

J

Jerry

I'm trying to use an Enterprise calendar created in Project Server
2007 to control working time through the Change Working Time tool in
Project Professional and it's not working. What's the best way to do
this?

Thank you,
Jerry McKenzie
 
D

Dale Howard [MVP]

Jerry --

Only the Project Server administrator can modify enterprise calendars, and
he/she must start the editing process from the Enterprise Calendars page in
PWA. Are you the Project Server administrator? If not, what are you
attempting to do with this enterprise calendar? Let us know and we will try
to help.
 
J

Jerry

Jerry --

Only the Project Server administrator can modify enterprise calendars, and
he/she must start the editing process from the Enterprise Calendars page in
PWA.  Are you the Project Server administrator?  If not, what are you
attempting to do with this enterprise calendar?  Let us know and we will try
to help.









- Show quoted text -

Hi Dale,

Thanks for responding to my post. I'm use to customizing the calendar
in Project Professional to show exceptions on a project-specific
basis. It sounds like in order to do the same thing in Project Server
2007, I'm going to have to create a custom enterprise calendar for
each project.

I work very closely with our Project Server admin, so I can pass along
the info regarding what needs to be done in PWA.

Thanks again and have a great holiday weekend!

Jerry McKenzie
 
D

Dale Howard [MVP]

Jerry --

The default permissions in Project Server 2007 do not allow project managers
to create their own custom calendars. Since you have a good working
relationship with your Project Server administrator, ask him/her to do one
of the following to help you with your unique scheduling needs:

1. Change the permission that denies project managers the ability to create
local Base calendars so that they can do this.

or

2. Create a custom enterprise calendar in the Project Server system that
you can use for your project.

Either one of these will solve your problem for you. Hope this helps.
 
K

Kris D

Dale,

I am the project manager with project server admin privileges. I've created the custom enterprise calendar. But, I can not for the life of me figure out how to associate it the specific project, or even each of the tasks of the project) it was created for using Project Server (not Professional).

Thanks,
Kris
I am trying to use an Enterprise calendar created in Project Server
2007 to control working time through the Change Working Time tool in
Project Professional and it is not working. What's the best way to do
this?

Thank you,
Jerry McKenzie
On Thursday, May 20, 2010 5:33 PM Dale Howard [MVP] wrote:
Jerry --

Only the Project Server administrator can modify enterprise calendars, and
he/she must start the editing process from the Enterprise Calendars page in
PWA. Are you the Project Server administrator? If not, what are you
attempting to do with this enterprise calendar? Let us know and we will try
to help.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top