Dear,
I change my Enterprise Calendars to be strt from 8 to 5:30 and 9 hour per day.
and ask all project manager to fix working time in there project to be same
my Enterprise Calendars.
but now i have problem that for example if i have 12 day task and i set my
complete work to 1 day in Assignment Details page after save, in my task page
the task progress will be 1.25 d, and if i change it to 1d and go to
Assignment Details it will be .89d.
can you help me
I change my Enterprise Calendars to be strt from 8 to 5:30 and 9 hour per day.
and ask all project manager to fix working time in there project to be same
my Enterprise Calendars.
but now i have problem that for example if i have 12 day task and i set my
complete work to 1 day in Assignment Details page after save, in my task page
the task progress will be 1.25 d, and if i change it to 1d and go to
Assignment Details it will be .89d.
can you help me