L
L8rdays
Hi I saw a reply to a similar question, but I need further assistance.
MSPS 2007 SP1, Infrastructure Update, Oct Cummulative,
Created custom Enterprise Field for a NUM field to equal the ID field data.
In an existing project, this field returns error# in non summary rows. If I
create a new project, this new field works fine.
Why can't or better yet How Can I get this to work in an existing project
plan.
The purpose is so that I can sort the My Tasks view by task id for a
simplier view as many resources have lots of tasks.
Thanks,
MSPS 2007 SP1, Infrastructure Update, Oct Cummulative,
Created custom Enterprise Field for a NUM field to equal the ID field data.
In an existing project, this field returns error# in non summary rows. If I
create a new project, this new field works fine.
Why can't or better yet How Can I get this to work in an existing project
plan.
The purpose is so that I can sort the My Tasks view by task id for a
simplier view as many resources have lots of tasks.
Thanks,