J
John Sitka
Hi,
I have a project where...
Enterprise Duration1 is entered in hours and rolls up as a sum in hours in Project and in PWA Views
Enterprise Duration2 is entered in hours and rolls up as a sum in hours in Project and in PWA Views
Enterprise Duration3 is entered in hours and rolls up as a sum in hours in Project BUT displays at the PWA task in days AND rolls up
as a sum in days and PWA Views
any ideas... Thanks
I have a project where...
Enterprise Duration1 is entered in hours and rolls up as a sum in hours in Project and in PWA Views
Enterprise Duration2 is entered in hours and rolls up as a sum in hours in Project and in PWA Views
Enterprise Duration3 is entered in hours and rolls up as a sum in hours in Project BUT displays at the PWA task in days AND rolls up
as a sum in days and PWA Views
any ideas... Thanks