Should Enterprise Custom fields values transfer between PWA and Project
Professional? If I edit an ECF (e.g. Health) in My Tasks on PWA and submit
the task, upon opening the task (and applying the update after reviewing and
noticing the change, e.g. Health changed to "Completed") in Project
Professional the values are not transferred (e.g. Health stays "Not
Specified"). This is similar the other way around; editing ECF in Project
Professional and publishing does not change the values in PWA.
I can't believe that this is as intended ?! Any insight?
Professional? If I edit an ECF (e.g. Health) in My Tasks on PWA and submit
the task, upon opening the task (and applying the update after reviewing and
noticing the change, e.g. Health changed to "Completed") in Project
Professional the values are not transferred (e.g. Health stays "Not
Specified"). This is similar the other way around; editing ECF in Project
Professional and publishing does not change the values in PWA.
I can't believe that this is as intended ?! Any insight?