G
Gertie
I want to create an Enterprise Custom Project Field that does the following:
1. Looks at Enterprise Task Field A - if any indicator in Field A is Red,
the project field is red; if no indicators in Field A are Red, it looks at
Enterprise Task Field B.
2. Looks at Enterprise Task Field B - if any indicator in Field B is Yellow,
the project field is yellow; if no indicators in Field B are yellow, it looks
at Enterprise Task Field C.
3. Looks at Enteprise Task Field C - which should all be green, so the
project field is green.
Assuming my general logic is correct as described (I hope), then is it
better to actually look at Task Field C, or better to just default to Green?
If no tasks in Field A are red, and no tasks in Field B are yellow, then the
only option is for all tasks in Field to be Green.
Thanks!
1. Looks at Enterprise Task Field A - if any indicator in Field A is Red,
the project field is red; if no indicators in Field A are Red, it looks at
Enterprise Task Field B.
2. Looks at Enterprise Task Field B - if any indicator in Field B is Yellow,
the project field is yellow; if no indicators in Field B are yellow, it looks
at Enterprise Task Field C.
3. Looks at Enteprise Task Field C - which should all be green, so the
project field is green.
Assuming my general logic is correct as described (I hope), then is it
better to actually look at Task Field C, or better to just default to Green?
If no tasks in Field A are red, and no tasks in Field B are yellow, then the
only option is for all tasks in Field to be Green.
Thanks!