J
julie
Why is it that when I enter the following formula, found in the Server 2003
Application Configuration Guide, I get an error on any schedule that doesn't
have a baseline set. I would expect to get a "No baseline" message returned
instead I get a #Error.
Switch(Len(CStr([Baseline Finish]))<3,"No baseline",Projdatediff(Baseline
finish],[Finish])/480>=5,"Late by more than 5 days",ProjDateDiff([Baseline
Finish],[Finish])/480>0,"late",True,"On Schedule")
Application Configuration Guide, I get an error on any schedule that doesn't
have a baseline set. I would expect to get a "No baseline" message returned
instead I get a #Error.
Switch(Len(CStr([Baseline Finish]))<3,"No baseline",Projdatediff(Baseline
finish],[Finish])/480>=5,"Late by more than 5 days",ProjDateDiff([Baseline
Finish],[Finish])/480>0,"late",True,"On Schedule")