Enterprise Field Examples

L

lmcgahee

I am working on defining enterprise fields and outlin codes for projects,
resources and tasks and was wondering if anyone had an example structure that
they have used for each of these areas to help generate some discussion with
my project managers.

I appreciate any assistance available.
 
D

Dale Howard [MVP]

Larry --

If you want something free, you should download the Project Server 2003
Application Configuration Guide.pdf from Microsoft at:

http://www.microsoft.com/downloads/...ad-6217-4568-be01-c3c3c907a526&DisplayLang=en

If you want an in-depth treatment of how to completely configure and use
Project Server, including how to create useful enterprise custom fields and
outline codes, you might consider purchasing our two books on Project Server
2003, available for purchase by clicking the URL in my signature block.
Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the books on Project Server"
 
T

TGG

Larry,

I could give you a laundry list of stuff like Business Value, Business
Sponsor Org and such. The problem I've run into with defining enterprise
fields centers around who owns the value for a given field. If the answer is
not the project manager, then you are going to have to involve more people in
the project setup process.

I would advise starting small and letting it grow. We did the opposite and
wound up frustrating the PMs when they didn't know what value was supposed to
go in a given field.

Fields that have worked well have three characteristics. First, the PM
understands the purpose of the information. Second, it is to be used to
group projects, resources and tasks in some way familiar to the organization.
Third, it can also be used to filter the information to create a specific
view of the portfolio.

So, in the end, I think we had about 10 really useful fields. Indicators
for budget, schedule, project risk and overall Project status. Business
Sponsor, Business Value, Project Size (we have internal processes based on
sizing), Project Status(Pipeline, Planning, Active, Completed, Canceled) and
two others that escape me.

I hope this helps.
TGG
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top