MS Project Server 2003: I have used the 'enterprise text3' field to put in a
custom value...viewable in the timesheet entry view. However, when I change
the value in my project (save and then publish)...I don't see the new value
on my task timesheet view...it still contains the old value.

What am I doing wrong?
 
D

Dale Howard [MVP]

Kevin --

If you enter the value in the Microsoft Project plan, you must click
Collaborate - Publish - Republish Assignments, select the "Overwrite actual
work entered by resources" option, and then click OK. Doing so will "push"
the new value to the timesheet. Hope this helps.
 
K

Kevin

Thanks Dale...quick response...that worked.

Dale Howard said:
Kevin --

If you enter the value in the Microsoft Project plan, you must click
Collaborate - Publish - Republish Assignments, select the "Overwrite actual
work entered by resources" option, and then click OK. Doing so will "push"
the new value to the timesheet. Hope this helps.
 