S
Stan
Hi,
We work with Project Server 2007. As an administrator, I opened the
Enterprise Calendars from PWA to modify the Standard calendar and make the
settings available for all the connected users.
I also opened Enterprise Global from PWA and changed settings in Calendar
and Schedule tabs, and saved Enterprise Global to server.
When a user connects to the server with Project Professional 2007, the
standard calendar is the same than the one in the server (expected behaviour)
but the settings in Tools Options Schedule and Calendar tabs are not the same
(unexpected behaviour).
This cause a problem because the settings (task types and so forth) are not
enforced for all users, and informations coming from "Change working time"
and Calendar tab (tools option) are not consistent.
Do you know how to manage this ?
Thanks.
Stan
We work with Project Server 2007. As an administrator, I opened the
Enterprise Calendars from PWA to modify the Standard calendar and make the
settings available for all the connected users.
I also opened Enterprise Global from PWA and changed settings in Calendar
and Schedule tabs, and saved Enterprise Global to server.
When a user connects to the server with Project Professional 2007, the
standard calendar is the same than the one in the server (expected behaviour)
but the settings in Tools Options Schedule and Calendar tabs are not the same
(unexpected behaviour).
This cause a problem because the settings (task types and so forth) are not
enforced for all users, and informations coming from "Change working time"
and Calendar tab (tools option) are not consistent.
Do you know how to manage this ?
Thanks.
Stan