Hello, we are running Professional and Server 2003. We are using Enterprise
Outline Code 1, renamed Task Number, for the team members to reference in
timesheets. The problem is that the numbers are summed in the summary tasks.
Is there a way to turn the summing function off? Or do we have to use a Text
Code and republish all of the projects. Any help is appreciated.
Thanks,
DC
Outline Code 1, renamed Task Number, for the team members to reference in
timesheets. The problem is that the numbers are summed in the summary tasks.
Is there a way to turn the summing function off? Or do we have to use a Text
Code and republish all of the projects. Any help is appreciated.