C
CarharttRandy
We are currently using MS Project 2003 and PWA 2003. We currently have 12-15
Project Managers with about 40+ projects publushed out to the server. Our
base calendar (that we created) uses 7.5 hour work days (which coincides with
our work day of 8-4:30 with an hour break). To make it easier on PMs, we
want to change our "Base Calendar" back to 8 hour days. My question is:
What ramifications will making this change have on the 40+ projects that are
already openend and published? Thanks!
Project Managers with about 40+ projects publushed out to the server. Our
base calendar (that we created) uses 7.5 hour work days (which coincides with
our work day of 8-4:30 with an hour break). To make it easier on PMs, we
want to change our "Base Calendar" back to 8 hour days. My question is:
What ramifications will making this change have on the 40+ projects that are
already openend and published? Thanks!