Hi
What kind of Formula do I have to use (in a Enterprise Project Field) for
the calculating of the Cost of a Project in a year ?
For example the Field has to show for Project X:
1000$ cost in 2005.
thanks..
 
J

Jerry

BTW

You can use Portfolio Analyzer to see the yearly cost. Its very
simple. Do you know how to use PA in Project Web Access.

Regards

Jerry
 
M

MAT

Hi Jerry.
I think I asked the question false.
I need to calculate the costs of one year just like in portfolio-views.
But I have to use this feld in views in Projectcenter.
So I need a formula that finds the cost (or actual cost) of a year. I dont
need the total cost.
Thanks. MAT
 