C
Chris
I created an Enterprise Project Duration Field using a formula where
FIELDNAME = [DURATION] to see if I could replicate the standard Duration that
is in the views for the Projects. I did this so I could create a report
using our Cognos BI tool to show the duration of a project. The result when
placing this in a view in Project Server is 0d, although the project has a
duration of 217d. How can I replicate the Duration (and the % Work Complete
field for that matter) in a Enterprise Project custom field?
Thanks!
FIELDNAME = [DURATION] to see if I could replicate the standard Duration that
is in the views for the Projects. I did this so I could create a report
using our Cognos BI tool to show the duration of a project. The result when
placing this in a view in Project Server is 0d, although the project has a
duration of 217d. How can I replicate the Duration (and the % Work Complete
field for that matter) in a Enterprise Project custom field?
Thanks!