M
MAS
I have an enterprise task level custom field that is an formula. I would like
to have a total of this field available at the project level. I am
determining if the task has an internal or external resource. If internal
then it is an internal cost if not it is an external cost. At a summary level
I could have tasks that were performed by both internal and external so I
have specified that the value should be summed for summary levels. How can I
capture this field that is summary for the entire proejct?
Thank you in advance for your help.
to have a total of this field available at the project level. I am
determining if the task has an internal or external resource. If internal
then it is an internal cost if not it is an external cost. At a summary level
I could have tasks that were performed by both internal and external so I
have specified that the value should be summed for summary levels. How can I
capture this field that is summary for the entire proejct?
Thank you in advance for your help.