Enterprise Resource Calendar

R

Robert

Hello,
Is it possible to give Project Managers the permission to edit their
resources' calendars without giving them the permission to edit all the
Enterprise resource data?
Thanks for your help
 
D

Dale Howard [MVP]

Robert --

No, there is no separate permission that allows a manager to only edit their
resources' calendars. If a manager can edit the calendar, he/she can edit
anything else about the resource. Hope this helps.
 
R

Robert

Dale,
Thanks for confirming what I suspected...

Dale Howard said:
Robert --

No, there is no separate permission that allows a manager to only edit
their resources' calendars. If a manager can edit the calendar, he/she
can edit anything else about the resource. Hope this helps.
 