É
飞鸿
Our company's actual situation is like this,
1,Many Project Managers couldn't logon to Project Server to publish plans
via Internet Explorer,but via Email to system administrator.
2,One Resource usually does not belong to the only Project Plan but also
other plans.And also Different Project Plans are managed by different
persons.This means One Resource is not managed by the only Project
Manager,but also the other Project Managers.
Now our problem is if One Resource is in different Project Plans and a
manager has requested the system administrator to change the Enterprise
Resource Calender,it'll got affected on the other plans which also contain
the same Resource. But the other Project Manager don't know this.
We wanna know how to solve this problem? Thanks extremely!
1,Many Project Managers couldn't logon to Project Server to publish plans
via Internet Explorer,but via Email to system administrator.
2,One Resource usually does not belong to the only Project Plan but also
other plans.And also Different Project Plans are managed by different
persons.This means One Resource is not managed by the only Project
Manager,but also the other Project Managers.
Now our problem is if One Resource is in different Project Plans and a
manager has requested the system administrator to change the Enterprise
Resource Calender,it'll got affected on the other plans which also contain
the same Resource. But the other Project Manager don't know this.
We wanna know how to solve this problem? Thanks extremely!