Steven --
To set nonworking time such as vacation on a resource's calendar, the
someone with administrator permissions must do the following in Project
Professional 2007:
1. Click Tools - Enterprise Options - Open Enterprise Resource Pool.
2. In the Project Center page, select the option checkbox for the resource
in questiona and then click the Open button.
3. Double-click the name of the resource in the Resource Sheet view in
Project Professional 2007.
4. On the General page of the Resource Information dialog, click the Change
Working Time button.
5. In the Change Working Time dialog, click the Exceptions tab if
necessary.
6. In the calendar at the top of the page, select the dates for nonworking
time.
7. In the data grid at the bottom, enter a name for the nonworking time,
such as Vacation and then press the down arrow key to navigate to the next
line.
8. Notice that the system enters the nonworking time as specified in the
calendar.
9. Click the OK button to close the Change Working Time dialog.
10. Click the OK button to close the Resource Information dialog.
11. Save and close the Enterprise Resource Pool.
After entering nonworking time, such as vacation, Project Server 2007 will
automatically reschedule task work for the resource around the nonworking
time in all enterprise project to which the resource is assigned. If you
eventually intend to enter nonworking time using the PWA timesheet, the
system will NOT add the nonworking time to each resource's calendar in the
Enterprise Resource Pool. Hope this helps.