I am trying to analyze resource requirements by skillset using the portfolio
analyzer. I have created custom enterprise resource outline codes in the
enterprise global (multi-value fields) and assigned these codes to resources
in the resource global. It seems to be fine on the Project Professional side
but when I try to use the Portfolio Analyzer to analyze resource availabliity
by skillset, the codes appear but have no value. Do I have to extend the
portfolio analyzer or is there something else that I need to do to make this
work?
analyzer. I have created custom enterprise resource outline codes in the
enterprise global (multi-value fields) and assigned these codes to resources
in the resource global. It seems to be fine on the Project Professional side
but when I try to use the Portfolio Analyzer to analyze resource availabliity
by skillset, the codes appear but have no value. Do I have to extend the
portfolio analyzer or is there something else that I need to do to make this
work?