We have an unusual, somewhat rare occurrence in MSPS 2007. A project
manager has a resource on their schedule that has had their record
recently updated. When the PM looks at the Resource Sheet data, the
changes are not displaying. However, when another PM opens the same
schedule and looks at the Resource Sheet, the data appears to be
updated. When the first PM closes and opens the schedule, the data
changes never appear in his view, and when he publishes, any data
associated with the resource is the old data, not the new.
We've seen this in pre-SP2 and post-SP2, but it's sporadic. Also,
when the schedule is opened from different entry points (from the
desktop client on a laptop, or from a Remote Desktop Connection), the
results may or may not be the same.
We think that maybe there is a cached copy of the resource record
(similar to a cached copy of the schedule) that is not being updated
when the PM opens the schedule. Has anyone seen this?
manager has a resource on their schedule that has had their record
recently updated. When the PM looks at the Resource Sheet data, the
changes are not displaying. However, when another PM opens the same
schedule and looks at the Resource Sheet, the data appears to be
updated. When the first PM closes and opens the schedule, the data
changes never appear in his view, and when he publishes, any data
associated with the resource is the old data, not the new.
We've seen this in pre-SP2 and post-SP2, but it's sporadic. Also,
when the schedule is opened from different entry points (from the
desktop client on a laptop, or from a Remote Desktop Connection), the
results may or may not be the same.
We think that maybe there is a cached copy of the resource record
(similar to a cached copy of the schedule) that is not being updated
when the PM opens the schedule. Has anyone seen this?