We are changing the std rate for our IT resources in 2010. I've noticed that
when I change the rate, the costs per task that were already completed in
2009 change to the new rate also. How can you keep the tasks that were
completed in 2009 at the 2009 rate and all uncompleted tasks going into 2010
at the new rate?
Thanks for any help I can get on this issue.