I am working with PS 2007, when I open the Enterprise Resource Pool to change
a resources's availability. I am taken to PWA's Resource Center and I do not
see anything related to availability.

Any ideas??

Doug
 
D

Dale Howard [MVP]

Doug --

While viewing the Resource Center page within Project Professional 2007,
select the option checkbox for the resource(s) you want to edit and then
click the Open button. This will open the Enterprise Resource Pool with the
resource checked out for editing. The Max. Units value in the Resource
Sheet is the column you wish to edit. When finished editing, save and close
the Enterprise Resource Pool. Hope this helps.
 