R
Ray Chiu (a1ahardware.florida at gmail)
SYMPTOM
=======
I wanted populate MSPS07 with enterprise projects, however, I received the
message above.
The message continues with:
Enterprise Standard Calendars are Needed.
Enterprise standard calendars are required to:
Build a team for a non enterprise project
Save a non-enterprise project into the server
Import resources to the enterprise
This may result in changes to schedule dates. Do you want to continue?
BACKGROUND INFORMATION
======================
I thought I created "Enterprise Calendars" via PWA through Server Settings
-> Enterprise Calendars (required Project Pro to be connected to EPM). Upon
closer inspection, these are branded in Project Pro as 'Base Calendar'. I
would guess these are not 'Enterprise Standard Calendars' That being said I
am not sure how 'Enterprise Standard Calendars' are created (I don't recall
these in the 2003 version, however, I could be wrong).
When saving the project to MSPS07, there is a drop down box and I can choose
from the list of 'Enterprise Calendars' that I configured earlier today.
QUESTIONS
=========
I have tried to do some research in this Newsgroup and MSDN: I hope that I
have taken due diligence before posing my questions:
Q1) What is the cause of the message and how do I remedy this? I would have
thought that selecting one of the 'Enterprise calendars' would be enough,
however there is something missing that I have not configured.
Q2) If I were to choose to continue, I don't think this would hurt because I
do not plan to use non-enterprise projects or import resources to the
enterprise. Is this assessment correct?
=======
I wanted populate MSPS07 with enterprise projects, however, I received the
message above.
The message continues with:
Enterprise Standard Calendars are Needed.
Enterprise standard calendars are required to:
Build a team for a non enterprise project
Save a non-enterprise project into the server
Import resources to the enterprise
This may result in changes to schedule dates. Do you want to continue?
BACKGROUND INFORMATION
======================
I thought I created "Enterprise Calendars" via PWA through Server Settings
-> Enterprise Calendars (required Project Pro to be connected to EPM). Upon
closer inspection, these are branded in Project Pro as 'Base Calendar'. I
would guess these are not 'Enterprise Standard Calendars' That being said I
am not sure how 'Enterprise Standard Calendars' are created (I don't recall
these in the 2003 version, however, I could be wrong).
When saving the project to MSPS07, there is a drop down box and I can choose
from the list of 'Enterprise Calendars' that I configured earlier today.
QUESTIONS
=========
I have tried to do some research in this Newsgroup and MSDN: I hope that I
have taken due diligence before posing my questions:
Q1) What is the cause of the message and how do I remedy this? I would have
thought that selecting one of the 'Enterprise calendars' would be enough,
however there is something missing that I have not configured.
Q2) If I were to choose to continue, I don't think this would hurt because I
do not plan to use non-enterprise projects or import resources to the
enterprise. Is this assessment correct?