Enterprise tags

K

Ken

In the Task Form a tag is showing up after the prodecessor and successor
names. The tag is (enterprise). This isn't allowing me to use the pulldown
and pick a task as a predecessor or successor. Where is the switch to delete
this tag form each task?
 
A

Andrew Lavinsky

Are you in PWA? If so, you can't modify predecessor and successor in a Project
Detail view.

If you're in Project, it sounds like your Administrator created a field called
Predecessor and made it calculated. Right click on the header of the column,
and check if there is a formula (which would be greyed out) for that field.
If so, then talk to your Administrator.

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 