A
Allen
Hi
I have defined several Enterprise Task Outline Codes and one in
particular is driving me bananas.
The list is defined on two levels (Internal and External tasks on
level one, sub tasks on level two) . When the project managers try to
add it to tasks, the cell will not drop down a list, as the other
outline codes do. I can't see why not.
Other smaller questions:
How do I get rid of 'dead' enterprise outline codes.
How do I create an enterprise task outine code where the PM can just
type in a value, like 'order number'. I can create them, but then
can't put values against them, as it says they're not in the list
(what list, I want just text!).
MTIA
Allen
I have defined several Enterprise Task Outline Codes and one in
particular is driving me bananas.
The list is defined on two levels (Internal and External tasks on
level one, sub tasks on level two) . When the project managers try to
add it to tasks, the cell will not drop down a list, as the other
outline codes do. I can't see why not.
Other smaller questions:
How do I get rid of 'dead' enterprise outline codes.
How do I create an enterprise task outine code where the PM can just
type in a value, like 'order number'. I can create them, but then
can't put values against them, as it says they're not in the list
(what list, I want just text!).
MTIA
Allen