Mark E --
You will need to do the following:
1. Log into Project Server through Microsoft Project Professional with
administrator permissions
2. Click Tools - Open Enterprise Global
3. Click Tools - Customize - Enterprise Fields
4. Select the Task option at the top of the dialog
5. Select the Type of task field you wish to customize, such as Cost, Date,
Duration, Text, etc.
6. Select the field you wish to customize, then click the Rename button
7. Give the custom field a new Name and then click OK
8. Customize the field in the manner you wish, such as with a Formula or a
Value List
9. Click the OK button
10. Save and close the Enterprise Global
11. Close and relaunch Microsoft Project Professional
From this point forward, you can now customize Tables and Views in Microsoft
Project Professional and customize Views in Project Web Access to display
this custom field. Hope this helps.