Hello NG,

anybody used the EnterpriseCustomFieldValueUpdate pds extender (SAP
connector) method to update task fields (e.g 188744284 Task Enterprise Cost
6) on a ProjectServer 2003 with SP1and got a populate view problem ?
The values won´t publish so i don´t see them e.g in Project Professional,
but i can see them in the MSP_TEXT_FIELDS table.
I also used the ViewPopulator tool, the standard PDS
ResourceViewTablesCreate method and i publish the project with Project
Professional 2003, but always the same no new values at all.

On ProjectServer 2003 with SP2a everything works fine for me, i don´t know
if the service pack matters, it´s the only difference i can find between
those 2 systems.

Any help appreciated